题目信息
Machines X and Y run at different constant rates, and machine X can complete a certain job in 9 hours. Machine X worked on the job alone for the first 3 hours and the two machines, working together, then completed the job in 4 more hours. How many hours would it have taken machine Y, working alone, to complete the entire job?
A:18
B:13

C:7

D:4

E:3

参考答案及共享解析

共享解析来源为网络权威资源、GMAT高分考生等; 如有疑问,欢迎在评论区提问与讨论
本题耗时:
已选答案:
正确答案:
A:18
Algebra Applied problems
Machine X can complete the job in 9 hours, so it completed
of the job before machine Y started working. Since machine X worked 4 more hours, it completed
of the job, which left
of the job for machine Y to do during the 4 hours it worked together with machine X to complete the job. At this rate, machine Y would take
= 18 hours to do the entire job working alone.
Alternatively, machine X can complete the job in 9 hours, so it completed
of the job before machine Y started working. This leaves
of the job, which took machines X and Y, working together, 4 hours to complete. So, if working together the machines took 4 hours to complete
of the job, it would take them 6 hours to do the whole job working together. Furthermore, rates are additive, so we should convert working times to rates. Machine X's rate is
jobs per hour. Both machines together have a rate of
jobs per hour. We must determine machine Y's individual rate
for the whole job. First, add machine X's rate to machine Y 's rate to get the combined rate. Then,

The correct answer is A.
Machine X can complete the job in 9 hours, so it completed




Alternatively, machine X can complete the job in 9 hours, so it completed







The correct answer is A.